Q&A Closing project or phase

Mock PMP Exam Questions:1. You are the project manager of the Quick WeightLoss Mix Project. The project is to create the right mix of ingredients for the herbal pills that help to reduce the weight within 6 weeks. You have found the right formula for the weight loss pills. You are now preparing to close the project. Which of the following is not an input to the Close Project or Phase process?

A. Project management Plan
B. Project deliverables validated through the quality control processes
C. Final project audits
D. Acceptance Criteria

Correct Answer: B. Validated deliverables are first sent to Verify Scope to become Accepted Deliverables.

2. You have reached the end of the project. To end a project, which process must be performed last:

A. Verify Scope
B. Close Project or Phase
C. Close Procurements
D. Complete Project

Correct Answer: B.

3. What is the correct order of performing the processes?

A. Perform Quality Control, Close Project or Phase, Close Procurements
B. Verify Scope, Perform Quality Control, Close Project or Phase, Close Procurements
C. Perform Quality Control, Verify Scope, Close Project or Phase
D. Verify Scope, Perform Quality Control, Close Procurements

Correct Answer: C.

4. Who can authorize the closure of a project?

A. Sponsor
B. Project Manager
C. Functional Manager
D. Customer

Correct Answer: A. The Sponsor was the one who sanctioned the project, so he/she must be the one to formally accept and close the project.